Connecting the grids of the “Dąbska” and “Gierczak” district heating plants in Szczecin
Company: Szczecińska Energetyka Cieplna
Status: completed
Implementation time frame: January 2009 - December 2009
Project total value: PLN 2,31 MM
Source of funding: own funds
Project objectives:
- Optimise the production and supply of heat from the “Dąbska” District Heating Plant
- Include in the district heating network the parts of the city that currently have no access to system heat
Project benefits:
- Decommission the less efficient heating plant Gierczak and assigning its tasks to the Dąbska plant
- Reduce the prices of heat in the area served by the heating plant Gierczak by approx. 15%
Tasks completed:
- Build 1.4 kilometre long district heating infrastructure to connect the grids
- Build a pipeline that will supply heat to the newly built residential and services buildings