Company: SEC Region
Status: completed
Completition time: May 2009 – September 2010
Total project value: PLN 3.59 million
Source of funding: funds from the European Regional Development Fund through the Implementing Authority – National Fund for Environmental Protection and Water Management launched under the Sectoral Operational Programme Infrastructure and Environment 2007 – 2013.
Project objectives:
- upgrading the infrastructure to increase the quality and efficiency of heat production,
- adapting heat plants to new environmental norms and standards for reducing air emissions,
- reducing the demand for electricity.
Benefits of the Project:
- improving environmental norms and standards,
- ensuring the profitability of the heating system,
- provision of a year-round hot water supply for customers supplied directly from the district heating network thanks to year-round operation of the district heating plant.
Scope of tasks completed:
- refurbishment of existing boiler,
- installation of a new boiler with a thermal output of 8 MW,
- installation of a new flue gas dedusting system,
- construction of a new dust and slag transport system,
- construction of a new thermal-hydraulic system with the installation of new circulation and boiler pumps,
- construction of an automation system,
- construction of a new water treatment plant for technological needs.