Modernization of district heating infrastructure in Strzelce Krajeńskie

Company: SEC Region

Status: completed

Time of completion: June 2014 – October 2014

Total project value: PLN 2.38 million

Source of funding: company’s own funds

Project objectives:

  • liquidation of inefficient local boiler houses,
  • construction of a district heating network and five heat substations.

Benefits of the Project:

  • improving environmental norms and standards,
  • ensuring trouble-free operation of the system,
  • improve the profitability of the operation of the district heating system,
  • create opportunities to attract new heat consumers.

Scope of tasks completed:

  • construction of a district heating network with a total length of over 1720 m,
  • construction of five heat substations,