Company: Szczecińska Energetyka Cieplna
Status: completed
Completion time: July 2014 – November 2014
Total project value: PLN 1.3 million
Source of financing: company’s own funds
Project objectives:
- ensuring trouble-free system operation,
- utilising the strengths of heating companies to achieve greater profitability in heat production at different times of the year.
Benefits of the Project:
- improve the profitability of the operation of the district heating system,
- stabilising prices for end users,
Scope of tasks completed:
- construction of an underground and overhead district heating network connecting the district heating systems of Słubice and Frankfurt (Oder)
with a total length of 622 m.