Heat is not just system heat

Heat is not just system heat

.
It is innovative energy infrastructure solutions as well as state-of-the-art energy realisations available on the market. Tailor-made energy concepts based on heating and cooling for new urban areas, buildings and industry. These include low-temperature networks, waste heat recovery solutions. If you are looking for a partner for sustainable solutions in the areas of energy, heating and cooling, find out more about our products and services.

We will take care of the rest. Write to us at biznes@sec.com.pl and you will be contacted by a member of the Sales Department, who will also be your personal contact person.

What does the connection process look like step by step?

If you are planning to connect your business to the district heating network, we will help you to go through the connection process smoothly.

Application

.
The completed and complete application for the determination of the conditions for connection to the district heating network, together with the attachments, should be submitted to the SEC.

Documents

.
Submitted documents are checked for correct completion and completeness of the application and annexes. The date of submission is the date on which a correctly completed and complete application is received by the SEC. If deficiencies or irregularities are found, the applicant will be asked to correct and/or complete the application – only the corrected forms can be considered for merit.

Analysis of the application

.
In the next stage, SEC analyses the application in order to ascertain whether the technical and economic conditions for connecting the facility to the district heating network exist. In the event of a positive opinion, the SEC determines the requirements for connection to the district heating network, which are sent in writing to the applicant.

Connection process

If the technical and/or economic conditions for connection are not met, SEC may refuse to provide the service. The applicant and the President of the Energy Regulatory Office (URE) will be notified of this. The connection process begins after the contract is concluded and may take
up to 12 months.

Conditions for connection

.
The determination of connection conditions is free of charge and their validity lasts for 2 years from the date of issue.

Contract

.
SEC prepares, agrees and signs a connection agreement with the customer, which specifies, among other things, the obligations of the parties, the scope of work, deadlines, SEC’s title to the property (in particular the so-called transmission easement) and the amount of the connection fee and the manner of its payment.

Design work and implementation

.
The signed connection agreement is the basis for the commencement of design work and implementation of the connection of the facility to the district heating network.

Start-up of heat supply

.
A contract for the sale of heat and the provision of transmission services must be concluded or updated before the heat supply can be started.

Once all works under the connection contract have been completed and the heat meter has been accepted by the SEC, the heat supply to the connected building may be started at the request of the customer.

Attachments to download

Name

Annex 1 – application for definition of terms and conditions for connection to a district heating network

Pobierz

List of documents – conditions for connection of the facility to the district heating network

Pobierz

Annexes 2a and 2b applications for connection to a district heating network and conclusion of a connection agreement

Pobierz

The process of connecting to the district heating network

Pobierz