Company: Szczecińska Energetyka Cieplna
Status: completed
Time of completion: December 2014 – January 2016
Total project value: PLN 40 million
Source of funding: company’s own funds
Project objectives:
- connection of district heating systems of the city of Szczecin
Benefits of the Project:
- improvement of the City’s energy security,
- increase in competitiveness between heat producers,
- stabilisation of heat prices,
- maintaining heat supply to the Prawobrzeże district during the shutdown of CR Dąbska
- unique project on a European scale (target operation of 5 sources on a shared district heating network).
Scope of tasks completed:
- construction of a district heating network with a total length of over 5.5 km,
- construction of two pumping stations and modernisation of the pumping station at CR Dąbska.