Company: Szczecińska Energetyka Cieplna
Status: completed
Time of completion: June 2014 – June 2016
Total project value: PLN 13.5 million
Source of funding: company’s own funds
Project objectives:
- connection of the Thermal Waste Treatment Plant to the district heating network
Benefits of the Project:
- improvement of the City’s energy security,
- increase in competitiveness between heat producers,
- stabilisation of heat prices,
- new source connected to the district heating system, target operation of 5 sources on a shared district heating network.
Scope of tasks completed:
- construction of a district heating network with a total length of more than 2.6 km,
- modernization of the chamber A-14, including full automation and controllability of heat flow,