Connection of the Thermal Waste Treatment Plant

Company: Szczecińska Energetyka Cieplna

Status: completed

Time of completion: June 2014 – June 2016

Total project value: PLN 13.5 million

Source of funding: company’s own funds

Project objectives:

  • connection of the Thermal Waste Treatment Plant to the district heating network

Benefits of the Project:

  • improvement of the City’s energy security,
  • increase in competitiveness between heat producers,
  • stabilisation of heat prices,
  • new source connected to the district heating system, target operation of 5 sources on a shared district heating network.

Scope of tasks completed:

  • construction of a district heating network with a total length of more than 2.6 km,
  • modernization of the chamber A-14, including full automation and controllability of heat flow,